Implementation of Critical Path Method
(CPM) Technique to a Road Construction
Project in Jalgaon District, Maharashtra
Kushagra Raghav
Citation :
Kushagra Raghav, "Implementation of Critical Path Method
(CPM) Technique to a Road Construction
Project in Jalgaon District, Maharashtra," International Journal of Mathematics Trends and Technology (IJMTT), vol. 65, no. 8, pp. 104-111, 2019. Crossref, https://doi.org/10.14445/22315373/IJMTT-V65I8P511
Abstract
Road Construction Industry is always looking to extend its effectiveness and efficiency to a greater
limit while using its techniques and methods. This study deals with managing the resources used in an effective
way and minimizing the cost. The primary data has been collected from a private construction company which
has various infrastructure projects running. The present work of the research paper is based upon the data of a
Jalgaon District, Maharashtra road construction project, in which there are various activities and approaches
available for different options to the contractor. Considering the project as a network we use CPM technique to
achieve a critical path of the network by dividing the road construction into various number of operations, thus
arriving at a critical path which is the longest path as it will involve all the critical activities required to
complete but it will also be with least number of days taken. The solution provided by this technique is such that
it gives the company an insight towards the complete duration of the project and specific activities that need
precise attention regarding delays. Thus, the study indicates that CPM techniques do result in gaining an
advantage for a contractor and the company.
Keywords
Critical Path Method, Program Evaluation Review Technique, Operations Research, Jalgaon, Road Construction, Maharashtra
References
[1] Boushaala, A. A. (2013). An Approach for Project Scheduling Using PERT/CPM and Petri Nets (PNs) Tools. International Journal of Modern Engineering Research (IJMER), 3200-3206.
[2] Md. Mijanoor Rahman, M. C. (2017). Fuzzy Numerical Results Derived From Crashing CPM/PERT Networks of Padma Bridge in Bangladesh. International Journal of Mathematics Trends and Technology (IJMTT), 603-607.
[3] Sujata Bala, S. M. (April 2017). Resource-allocation by histogram and time scale method with PERT and CPM. International Journal of Mathematics Trends and Technology (IJMTT), 263-269.